Solomon Islands: Solar Power Development Project
Sovereign (Public) Project | 48346-002
The Asian Development Bank is working with the Government of Solomon Islands and Solomon Power to convert electricity networks in five provinces almost entirely to solar power. The project will reduce the need for costly shipments of diesel to the provincial centers.
LATEST PROJECT DOCUMENTS
Project Name | Solar Power Development Project | ||||||||
Project Number | 48346-002 | ||||||||
Country | Solomon Islands | ||||||||
Project Status | Active | ||||||||
Project Type / Modality of Assistance | Grant | ||||||||
Source of Funding / Amount |
|
||||||||
Strategic Agendas | Environmentally sustainable growth Inclusive economic growth Regional integration |
||||||||
Drivers of Change | Gender Equity and Mainstreaming Governance and capacity development Knowledge solutions Partnerships Private sector development |
||||||||
Sector / Subsector | Energy / Renewable energy generation – solar |
||||||||
Gender Equity and Mainstreaming | Effective gender mainstreaming | ||||||||
Description | |||||||||
Project Rationale and Linkage to Country/Regional Strategy | |||||||||
Impact | Utilization of renewable energy has increased |
Project Outcome | |
---|---|
Description of Outcome | Supply of reliable, cleaner electricity from renewable energy sources |
Progress Toward Outcome | |
Implementation Progress | |
Description of Project Outputs | 1. Grid-connected solar power plant put into operation by SIEA
3. PMU renders efficient project management services 2. Business conditions created for private sector investment in solar home systems |
Status of Implementation Progress (Outputs, Activities, and Issues) | Land acquisition activities ongoing.
Procurement for main EPC contract ongoing. Bidding documents advertised 15 August 2017. PMU established. |
Geographical Location | Kirakira, Lata, Maluu, Munda, Tulaghi |
Safeguard Categories | |
---|---|
Environment | B |
Involuntary Resettlement | B |
Indigenous Peoples | C |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | |
Involuntary Resettlement | |
Indigenous Peoples | |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | |
During Project Implementation |
Responsible ADB Officer | Maxwell, Anthony |
Responsible ADB Department | Pacific Department |
Responsible ADB Division | Transport, Energy and Natural Resources Division, PARD |
Executing Agencies |
Ministry of Mines, Energy and Rural Electrification P.O Box G37, HONIARA, Solomon Islands |
Timetable | |
---|---|
Concept Clearance | 07 Nov 2014 |
Fact Finding | 07 Mar 2016 to 18 Mar 2016 |
MRM | 17 May 2016 |
Approval | 21 Nov 2016 |
Last Review Mission | – |
Last PDS Update | 25 Sep 2017 |
Grant 0514-SOL
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
21 Nov 2016 | 19 Jan 2017 | 05 Apr 2017 | 30 Jun 2021 | – | – |
Financing Plan | Grant Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 9.00 | Cumulative Contract Awards | |||
ADB | 2.24 | 21 Nov 2016 | 0.13 | 0.00 | 6% |
Counterpart | 6.76 | Cumulative Disbursements | |||
Cofinancing | 0.00 | 21 Nov 2016 | 0.04 | 0.00 | 2% |
Grant 0515-SOL
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
21 Nov 2016 | 19 Jan 2017 | 05 Apr 2017 | 30 Jun 2021 | – | – |
Financing Plan | Grant Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 6.20 | Cumulative Contract Awards | |||
ADB | 0.00 | 21 Nov 2016 | 0.00 | 0.00 | 0% |
Counterpart | 0.00 | Cumulative Disbursements | |||
Cofinancing | 6.20 | 21 Nov 2016 | 0.00 | 0.00 | 0% |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB’s operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
SAFEGUARD DOCUMENTS See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
Title | Document Type | Document Date |
---|---|---|
Solar Power Development Project: Environmental and Social Monitoring Report (January-July 2020) | Environmental and Social Monitoring Reports | July 2020 |
Solar Power Development Project: Environmental and Social Monitoring Report (July-December 2019) | Environmental and Social Monitoring Reports | Dec 2019 |
Solar Power Development Project: Environmental and Social Monitoring Report (January-June 2019) | Environmental and Social Monitoring Reports | Jul 2019 |
Solar Power Development Project: Environmental and Social Monitoring Report (July-December 2018) | Environmental and Social Monitoring Reports | Jan 2019 |
Solar Power Development Project: Semi Annual Environmental and Social Monitoring Report (January-June 2018) | Environmental and Social Monitoring Reports | Aug 2018 |
Solar Power Development Project: Initial Environmental Examination | Initial Environmental Examination | Apr 2016 |
Solar Power Development Project: Resettlement Plan | Resettlement Plans | Apr 2016 |
EVALUATION DOCUMENTS See also: Independent Evaluation
None currently available.
RELATED PUBLICATIONS
None currently available.
Please contact Droumand Rupert on telephone number 39467 or by email (Droumand.Rupert@solomonpower.com.s), for the Role Statements of these positions to assist you in your applications. Your application must include; (i) a covering letter (ii) updated CV detailing your qualifications, relevant work experiences and referee details (iii) certified copies of certificates of your academic qualifications and/or professional trainings.
All applications must be addressed to: Senior Human Resources Business Partner, Solomon Power, P O Box 6, HONIARA. You can submit your application either in hard copy, which you can drop off at the Solomon Power Ranadi Office or by soft copy through the restricted email: recruitment@solomonpower.com.sb. Applications close at 4.30pm, on Friday 13th April, 2018.
Solomon Power thanks all applicants, and wishes to advice that only those who satisfy the Key Selection Criteria and are shortlisted for interview will be contacted. Therefore we will not be formally replying to all applications.
The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB’s decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
ADB Approves $15.2 Million Solar Project for Solomon Islands
ADB today approved financing to support the Government of Solomon Islands and Solomon Power to convert electricity networks in five provinces almost entirely to solar power.
TENDERS
Tender Title | Type | Status | Posting Date | Deadline |
---|---|---|---|---|
Environmental and Social Safeguards Specialist | Individual – Consulting | Closed | 30 Apr 2020 | 18 May 2020 |
Grant 0514-0515-SOL: Solar Power Development Project [W01] | Invitation for Bids | Closed | 18 Aug 2017 | 18 Oct 2017 |
CONTRACTS AWARDED
No contracts awarded for this project were found
PROCUREMENT PLAN
Title | Document Type | Document Date |
---|---|---|
Solar Power Development Project: Procurement Plan | Procurement Plans | Sep 2016 |