New Honiara Transformers

PROJECT DETAIL: Installation and commissioning of a new 33/11KV transformer and associated works at Honiara Power Station

BUDGET: SBD $6.2m

FUNDING SOURCE: SIEA

STATUS: Works are currently ongoing

ESTIMATED COMPLETION DATE: April 2015

A new transformer for Honiara power station will be installed and commisioned towards the middle of 2015. Enabling works to prepare the transformer bunds and pads are currently undertaken by a local firm. The new transformer will replace the old one Honiara transformer to ensure reliability and continued service over the coming years.