1. PROJECT DETAIL: Supply and installation of 2x100kW Diesel Power Generators and 1x415VAC switchboard
BUDGET: SBD $1.4m
FUNDING SOURCE: SIEA
STATUS:Tender Evaluations underway managed by Jacobs
ESTIMATED COMPLETION DATE: November 2015
2. PROJECT DETAIL: Extension work to existing building to accommodate the 2 new 100kW generator sets and associated equipment
BUDGET: SBD $1m
FUNDING SOURCE: SIEA
STATUS: Tender Evaluations completed awaiting contract formalisation
ESTIMATED COMPLETION DATE: 16 June 2015 (to be revised based on submission of program of works)